Milestones

First Stage Clearance : June 1995
DFR Submission : October 1995
Formation of Petronet India Ltd : June 1997
Incorporation of Petronet CCK Ltd : June 1998
Scheduled Project Period : 36 Months
Commencement of Project : June 1998
Pipe Line Laying Started : December 1999
Mechanical Completion : February 2002
Project Period : 3 Years   8 Months
Trial Runs : March   2002
Commercial Operation : 24th September 2002
Project Cost : Rs.350 Cr.